Most kitchen remodels start with cabinets and colors. This Thousand Oaks kitchen started with a different question: what is hiding in the ceiling and behind the walls, and how do we move it? The home is a two-story house, the kitchen was a U-shape that needed to open up, and the plan called for removing a soffit, extending a wall and relocating plumbing and electrical lines. Here is how that work came together in 4 to 5 weeks.
The Project at a Glance
- Location: Thousand Oaks, California
- Home: a two-story house, so the kitchen sits under a second floor
- Timeline: 4 to 5 weeks of construction
- Structure and utilities: soffit removed, wall extended, plumbing re-routed, electrical and plumbing relocated, with the work planned around joists and framing
- Finishes: gray shaker base cabinets and drawers, white upper cabinets, matte black bar pulls, a white countertop with soft gray veining, a glazed teal tile backsplash, hardwood floors and warm toe-kick lighting
You can see the finished space in the Thousand Oaks kitchen remodel gallery.
Why a Two-Story Home Changes the Kitchen Plan
When a kitchen sits under a second floor, the ceiling is more than a ceiling. It is the underside of the floor above, and the joists that carry that floor are also the path that plumbing, wiring and ducts often follow. In most two-story homes, moving a sink, a range or a drain line means working around those joists and the framing that surrounds them. A joist cannot be cut or notched like a piece of trim, because any change has to respect how the floor above is held up.
That is why the first questions on a project like this are not about cabinet color. They are about what is above the kitchen, what runs through the ceiling, and which walls can move.
The Hard Part: Re-Routing the Plumbing
The new layout gave the cabinets and appliances a clear place to sit, but it also meant the plumbing had to move. Drain lines need to slope toward the main line, vent lines have to connect properly, and supply lines have to reach the new fixture locations. In a two-story home all of that happens in the tight space between the floor framing, the walls and the rooms above.
Re-routing the plumbing was the part of this job that demanded the most planning. Everything else depends on it, because cabinets, counters and tile cannot be finished until the pipes behind them are in the right place and have passed inspection.
Taking Out the Soffit
A soffit is the boxed-in section above the cabinets that often hides pipes, wiring or ductwork. Removing it makes a kitchen feel taller and more open, which was the goal here. Our crew removed the soffit and extended a wall, and that reshaped the layout and gave the new cabinets and appliances a clear place to sit.
A soffit is also a closed box, so you only know what it holds once it is open. Anything inside has to be re-routed or protected before the ceiling is closed again. That is one reason we plan soffit removal together with the plumbing and electrical work instead of treating it as a separate demolition task.
Moving Electrical and Plumbing Together
When a kitchen layout changes, outlets, lighting and appliance connections move with it. On this project both the electrical and the plumbing were relocated, so the trades had to work in the right order around the same framing. Rough-in happens before the walls and ceiling are closed, and in California, relocating plumbing or electrical lines normally requires a permit and inspections before drywall goes up. Our kitchen permit guide explains what to expect.
Clean rough-in work is what lets the finish work go in without surprises. When the hidden parts are right, the visible parts follow a straight line.
Why the Order of Work Matters in a 4 to 5 Week Schedule
Four to five weeks is a short window for a kitchen that involves framing and utilities, so the sequence matters. The general order we follow looks like this:
- Protection and demolition, including the soffit.
- Framing changes, such as the extended wall and any work around the joists.
- Plumbing and electrical rough-in in the new locations.
- Inspection before anything is closed up.
- Insulation and drywall.
- Cabinets and countertops.
- Tile, flooring, lighting and final connections.
When the hidden work is planned before the first day, each trade hands off to the next without waiting. When it is not, a kitchen stalls. Our kitchen remodel timeline breaks down each phase.
The Finished Kitchen
The result is a brighter, cleaner U-shaped kitchen. Gray shaker base cabinets and drawers pair with white upper cabinets and matte black bar pulls. A white countertop with soft gray veining wraps the U-shaped layout and the peninsula, and a glazed teal tile backsplash adds color behind the stainless range. Tall white pantry cabinets stand beside a black stainless refrigerator, a garden window over the stainless sink brings in daylight, and warm toe-kick lighting glows under the base cabinets above the hardwood floors.
What Thousand Oaks Homeowners Can Take From This
- Ask what is above and inside before you lock the layout. A soffit, a joist or a second floor can decide what is possible.
- Treat plumbing moves as a main scope item. Moving a sink or a drain line is where a kitchen gets more complex than a like-for-like swap.
- Ask who handles permits and inspections. Relocated plumbing and electrical need both.
- Keep the trades under one team. Framing, plumbing and electrical all touch the same space, and they work best when one project manager coordinates them.
For cost expectations, RnD kitchen remodels run $35,000 to $150,000 depending on scope, and timing, material choices and selections can push the final cost higher. Layout changes that move plumbing, remove a soffit or touch framing add work compared with a like-for-like update, which is part of why the range is wide. Our kitchen planning guide covers the steps before construction, and you can read more about our kitchen remodeling services and home remodeling in Thousand Oaks.
FAQ
Frequently Asked Questions
Why does moving plumbing add so much to a kitchen remodel?
Moving a sink, dishwasher or drain line means new drain, vent and supply routes that must slope correctly and fit around the floor framing. It also adds permit and inspection steps and has to be finished before cabinets, counters and tile. That extra work is why layout changes cost more than a like-for-like update.
Can a soffit be removed in any kitchen?
Often, yes, but it depends on what is inside. A soffit can hide pipes, wiring, ductwork or framing. It has to be opened first so those items can be re-routed or protected before the ceiling is closed. Removing a soffit and extending a wall reshaped the layout of this Thousand Oaks kitchen.
Does a two-story home make a kitchen remodel harder?
It can. When a kitchen sits under a second floor, plumbing, wiring and ducts often run through the joist space, and joists cannot be cut or notched freely. Moving fixtures means planning around the joists and framing, so the layout and the utility routes need to be decided together.
Do you need a permit to relocate plumbing and electrical in a kitchen?
In California, relocating plumbing or electrical lines normally requires a permit and inspections before the walls and ceiling are closed. RnD handles the plans, permits and construction with one licensed team, so the inspections fit into the schedule.
How long does a Thousand Oaks kitchen remodel take?
This kitchen, with a soffit removal, a wall extension and relocated plumbing and electrical in a two-story home, took 4 to 5 weeks of construction. At RnD, kitchen construction is guaranteed in 28 days, and design, selections and permits come first.
Planning a Kitchen Remodel in Thousand Oaks?
Tell us what you want to change in your kitchen, including any walls, soffits or plumbing you would like to move. We will set up a free consultation, map out a realistic timeline for your scope, and give you a real number before work starts.
Ready to start your project?
Schedule a consultation meeting today and get your project on the go!
We are glad to address any inquiries you may have. Please write us a few words about your project and we’ll set up a meeting with one of our project managers.
- (805) 367-1965
- info@rndbuildersinc.com
- 21250 Califa St, Suite #214, Woodland Hills, CA 91367
- CA License #1081122
Tell us about your project
Our work
Completed Kitchen Remodeling Projects
Real homes RnD Builders finished across Los Angeles and Ventura County.
Kitchen RemodelThousand Oaks Kitchen RemodelView project
Kitchen RemodelThousand Oaks Kitchen Remodel – Project 5View project
Kitchen RemodelThousand Oaks Kitchen RemodelView project
Kitchen RemodelCalabasas Kitchen RemodelView project
Kitchen RemodelCamarillo Kitchen RemodelView project
Kitchen RemodelWestlake Village Kitchen RemodelView project
Kitchen RemodelLos Angeles Kitchen Remodel – Project 2View project
Kitchen RemodelLos Angeles Kitchen RemodelView project
Kitchen RemodelOxnard Kitchen RemodelView project
Kitchen RemodelSimi Valley Kitchen RemodelView project